Project Status reports unhealthy services
Last edited: 11/27/2025

If the project was recently restored, it can take up a couple minutes to become fully operational.
Services rely on the backend database. Unhealthy services can indicate a database being overloaded due to being undersized or not tuned appropriately.
- Review this troubleshooting doc to determine if it could be a resource issue.
- If services recover and become unhealthy again, there is likely a repeated issue overloading the database.
Possible resolutions:
- Restart the database in Project Settings (this may be only a temporary fix if the project is undersized / unoptimized).
- Increase project resources in Compute and Disk.
- Performance Tune the database.